  • Project Scope - Phase 1

    • Installation of underground utilities.
    • Building pad prep.
    • Installation of a new exercise classroom.

    Project Scope - Phase 2

    • Demolition and relocation of existing relocatable classrooms, rough grading, and installation of underground utility lines.
    • Construction of a new 24,000 square foot two-story classroom building.  The building will have 16 classrooms as well as student and staff restrooms.
    • Installation of underground utilities.

    Project Scope - Phase 3

    • Increment 3 - Renovation of the administrative building A, B-wing classrooms, and student courtyard.

    Completed on schedule and within budget!